Concrete works were carried out on the AB slab in the existing hall, cutting the joints on already concreted slabs. Grit removal works from the shipyard were done.
The loading of the packed grit was carried out, with separation and transport to the ship, by which the grit was further transported to a foreign country.
Remediation of old buried oil and rigid docks with waste removal was carried out, along with replacement of existing material with a cement mixture, delivery and filling of stone aggregate, and its leveling and planning. Demolition of 5 existing halls with waste material removal.
Currently, with planning and rolling, over 10.000 m3 of a crushed fraction of 02-63mm is filled.
Project value: 350.000€
Project details
- Project: Shipyard – Bijela – 2019
- Category: Other
- Client: Valgo Podgorica