The following works were carried out at this facility:
– mechanical excavation of the terrain around the hall with preparation and planning for concrete slabs around the hall
– complete atmospheric and fecal sewage around the facility with the installation of an oil separator
– construction of a supporting AB wall and fence around the hall
Currently, we are in the construction phase of this facility and the work is continuing according to the dynamic planning.
Project value: 75 500€